Updated February 2026

What is a DNO and why does it affect your EV charger installation?

The moment usually goes like this. You have chosen a charger, agreed a price, and expected a straightforward installation. Then the installer pauses and says they need to “submit a DNO application” or “wait for DNO approval”. Suddenly what you assumed was a one-day job involves an external organisation you have never heard of, an unknown timescale, and the uncomfortable suggestion that the installation might not proceed at all. This guide explains what a DNO is, why EV chargers specifically trigger its involvement, and what it means for you.

6
Licensed DNOs covering Great Britain
G100 notification only
Most domestic 7 kW installs
30–65 working days
Formal application: typical response

What is a DNO?

A Distribution Network Operator, usually shortened to DNO, is the company that owns and maintains the local electricity network in your area. That network runs from the local substation, along the cables under your street, to the electricity meter fixed to your property.

The DNO does not generate electricity and does not sell you electricity. Electricity generation is handled by power stations and renewable generators. Electricity retail supply is handled by companies such as Octopus Energy or British Gas, who bill you and set your tariff. The DNO sits in between, responsible for the physical infrastructure that delivers electricity to homes and businesses.

This distinction matters because most people assume their energy supplier controls everything related to electricity. In reality, your supplier cannot approve or refuse a new EV charger connection. Only the DNO can do that, because only the DNO is responsible for ensuring the local network remains safe and stable.

The six DNOs in Great Britain

In Great Britain there are six licensed DNOs, each operating a defined geographic region under regulation by Ofgem:

DNO regions — Great Britain

Schematic map — boundaries are approximate

SSENN ScotlandSP EnergyS ScotlandENWNW EnglandNorthernPowergridNE EnglandNGEDMidlands + SW+ S WalesUKPNLondon + SE+ East EnglandNIE
SSEN Distribution
N Scotland + parts of S England
SP Energy Networks
S Scotland + Merseyside
Electricity North West
Lancashire, Manchester, Cumbria
Northern Powergrid
Yorkshire, North East
National Grid ED
Midlands, SW England, S Wales
UK Power Networks
London, SE England, East England

SSEN Distribution also serves parts of southern England including Hampshire, Berkshire, and Wiltshire. Merseyside and parts of North Wales are served by SP Energy Networks. Northern Ireland is served by NIE Networks. Boundaries are schematic and approximate.

In Northern Ireland, the equivalent role is performed by NIE Networks.

The ownership boundary

The DNO owns the network up to and including the electricity meter. Everything after the meter — your consumer unit and internal wiring — belongs to you. EV charger installation sits exactly on that boundary, which is why the DNO must be involved. It is also important not to confuse local distribution networks with the national transmission system. The high-voltage transmission grid moves electricity long distances between regions. DNOs manage the lower-voltage networks that supply homes.

Why does an EV charger require DNO involvement?

A home EV charger represents one of the largest single electrical loads a domestic property is ever likely to connect. A typical 7 kW charger draws more power than an electric shower, an oven, or a kettle — and it does so continuously for several hours.

The local electricity networks serving most UK streets were designed decades ago around very different assumptions. They expected relatively modest, short-duration peaks from cooking and heating appliances, not sustained high loads from multiple houses charging vehicles simultaneously. Electric vehicles represent a step change in demand at street level, even if overall national generation capacity is sufficient.

Under the Electricity Act 1989, DNOs have a statutory duty to develop and maintain an efficient, co-ordinated, and economical system of electricity distribution. That duty is reinforced by the Distribution Connection and Use of System Agreement (DCUSA), which governs how connections are made and how network capacity is managed. In practical terms, a DNO must be satisfied that adding a new EV charger will not cause voltage drop, flicker, or overloading of equipment that supplies neighbouring properties. This assessment is about the shared network, not about whether your fuse box can cope.

Before an EV charger is connected, the installer must declare the additional load to the DNO. Depending on the circumstances, this happens in one of two ways — and understanding the distinction is the most important thing to take from this guide.

G100 notification — most domestic installations

Engineering Recommendation G100, published in 2020, was developed specifically to streamline the connection of domestic EV chargers. Under G100, an OZEV-approved installer can self-certify and connect a compliant smart charger without requiring advance DNO approval, provided the charger includes demand limiting measures (meaning it can reduce its draw if the local network is under stress). The installer notifies the DNO after installation with the technical details.

This is often described loosely as “DNO notification” rather than “DNO approval”. The key point is that the DNO does not make a decision in advance — it is informed, not consulted. The majority of single 7 kW home charger installations proceed this way.

Formal DNO connection applications — larger and more complex installs

When an installation falls outside the G100 framework — because of its size, the number of chargers, or a constrained local network — a formal connection application is required. This is a standard low-voltage demand connection application processed under the DNO’s own connection charging methodology (governed by DCUSA), not a G99 application. Engineering Recommendation G99 is a separate standard that applies specifically to generation equipment — solar PV, battery storage, and similar — connecting to the distribution network. It is not the relevant standard for EV charger demand connections.

A formal DNO connection application is typically required for:

A formal connection application requires active assessment and a decision from the DNO before installation can proceed. When an installer uses the phrase “DNO application”, it is worth asking specifically: “Is this a G100 notification or a formal connection application?” The answer determines your timeline.

When does a DNO application actually delay installation?

Delays occur when the installer cannot rely on G100 notification and must ask the DNO to assess the network in advance. Several common scenarios trigger this.

Realistic timescales

Most DNOs aim to assess straightforward low-voltage connection applications within 30 working days. More complex cases can take 45–65 working days. Where the DNO identifies that service upgrade or network reinforcement is needed, the overall process — including the works themselves — can extend to three to nine months. These are realistic planning horizons, not worst-case scenarios. If an installer flags a formal application may be needed, factor this into your timeline before committing to an installation date.

What happens during a DNO application?

From a homeowner’s perspective, the process usually follows a clear sequence.

As of 2025, most major DNOs have improved their EV processes significantly, with clearer guidance and shorter response times than were common in 2022 and 2023.

What can you do to reduce the risk of delay?

Find an OZEV-approved installer near you

OZEV-approved installers are required to be familiar with DNO notification and application requirements. Compare verified installers in your area — no cold calls, no middlemen.

Search all locations →

Frequently asked questions

Does every EV charger installation need DNO approval?

No. Most standard domestic 7 kW installations only require notification to the DNO under Engineering Recommendation G100. Formal DNO approval is only required in specific circumstances — for example, commercial sites, multiple chargers, or properties where the local network needs capacity assessment.

How long does a formal DNO connection application take in the UK?

For straightforward low-voltage connection applications, most DNOs aim to respond within 30 working days. More complex applications — where network reinforcement is being considered — can take 45–65 working days or longer. Where the DNO identifies that service upgrade or reinforcement works are needed, the overall lead time can extend to several months.

Who pays for DNO network reinforcement works?

If reinforcement is required solely because of your new connection, the cost is ordinarily passed to the applicant under the DNO's connection charging methodology. If the DNO determines that the network was already deficient and required upgrading regardless of your application, it may cover some or all of the cost.

Can I install an EV charger without telling the DNO?

No. Installations must be notified or approved in accordance with Engineering Recommendation G100 (for domestic smart chargers) or the DNO's formal connection process for larger installations. Failure to do so can breach BS 7671 and the Electricity Safety, Quality and Continuity Regulations 2002, and can cause difficulties with insurance and future property sales.

Further reading

Last updated: February 2026. DNO areas and regulatory framework correct as of publication. Verify current grant details at gov.uk.